What is a defined cost NEC4?

Under NEC4 PSC Option C, Defined Cost is the cost components in the Schedule of Cost Component less Disallowed Cost. The Prices are the lump sum prices for each of the activties on the Activity Schedule.

What is a defined cost?

Broadly speaking, Defined Costs are the actual costs incurred by the Contractor on the Works minus retention and any costs which would fall within the overheads covered in the Fee. From those are deducted “Disallowed Costs”. “Disallowed Cost” is defined by Clause 11.2(25).

What is included in the schedule of cost components?

This includes wages and salaries, payments to people for bonuses, overtime, sickness, holidays, travelling and relocation together with Equipment, Plant and Materials purchases, utilities charges, and financing.

What is NEC4 professional services contract?

The NEC4 Professional Service Short Contract (PSSC) is intended for use in the appointment of a supplier to provide professional services on smaller scale projects where sophisticated management techniques are not required.

What is working area overhead NEC?

Working Areas overhead percentage. A charge for overhead costs incurred within the Working Areas calculated by applying the percentage for Working Areas overheads stated in the Contract Data to the total of people items 11, 12, 13 and 14.

How does a target cost contract work?

A target cost contract is a type of cost reimbursable contract under which the contractor is paid the ‘actual cost’ (usually defined in the particular contract) it incurs in carrying out the works, but subject to a target cost which is agreed by the parties at the beginning of the project.

See also  Does MJ remember Peter?

How does NEC option C work?

Option C is a target cost contract with an activity schedule where the out-turn financial risks are shared between the client and the contractor in an agreed proportion. This document contains all the core and secondary option clauses, the schedules of cost components, and contract data relevant to an option C contact.

How does NEC option E work?

Option E allows the client to pay the actual cost of the contractor’s work on the project plus a pre-agreed amount for the contractor’s overheads and profit. In this option, the risk is largely borne by the client, because any additional costs above those predicted are reimbursable to the contractor.

What is a disallowed cost NEC3?

(25) Disallowed Cost is cost which the Project Manager decides. · is not justified by the Contractor’s accounts and records, · should not have been paid to a Subcontractor or supplier in accordance with his contract, · was incurred only because the Contractor did not.

What is NEC Option G?

An Option G, under the NEC3 Professional Services Contract provides an overarching arrangement that allows clients to: • Call off professional services on a flexible and non-committal basis over a longer term, enabling continuity and consistency of delivery after the expiry of the framework on 4th January 2021.

What is direct fee in NEC?

Compared to NEC2, NEC3 has two fee percentages; the direct fee, which is applied to the defined costs of the Contractors direct resources and the subcontracted fee percentage, which is applied to the defined costs of subcontracted work.

See also  How much money do you need to live comfortably in Canada?

How many types of NEC contracts are there?

There have been four editions, the first in 1993, the second in 1995, the third in 2005 and the most recent in 2017. The NEC3 was launched in 2005 and it was amended in April 2013. NEC4 was announced in March 2017 and has been available since June 2017.

How does NEC Option C work?

Option C is a target cost contract with an activity schedule where the out-turn financial risks are shared between the client and the contractor in an agreed proportion. This document contains all the core and secondary option clauses, the schedules of cost components, and contract data relevant to an option C contact.

What is a measure and value contract?

“Measure and value”, or “remeasurement” contracts, are contracts in which the amount payable to the contractor is determined by measuring the work actually done, and valuing it in accordance with the rates and prices set out in the contract in a bill of quantities, or schedule of rates.

What is PWDD?

The amount due is the Price for Work Done to Date (PWDD) less amounts to be paid by or retained from the Contractor. The PWDD is the total Defined Cost the Project Manager forecasts will have been paid by the next assessment date, plus the Fee.

What is NEC option F?

Option F is a cost reimbursable management contract where the financial risk is taken largely by the client. This document contains all the core clauses and secondary option clauses the schedules of cost components, and contract data, relevant to an option F contract.

See also  What can I do with old leather sofa?

What is an ECC payment?

Under the ECC there is no separate concept of a contract sum. The ECC uses the term Prices, which has a different meaning in each of the options: In Options A and C – Prices means each of the lump sum prices against each of the activities in the activity schedule.

What is a BoQ in construction?

Generally, the Bill of Quantities (BoQ) is drawn-up by the quantity surveyor (employer’s consultant) with construction information provided by the design team. The primary purpose of a BoQ is to ensure all tenderers are provided with a standardised document to price and submit a fair and accurate tender.

What is NEC4 option E?

The NEC4 Engineering and Construction Contract (ECC) Option E is a cost reimbursable type contract where the financial risk is taken largely by the client.

What is a defined cost NEC4?

Under NEC4 PSC Option C, Defined Cost is the cost components in the Schedule of Cost Component less Disallowed Cost. The Prices are the lump sum prices for each of the activties on the Activity Schedule.

What does JCT stand for in construction?

The Joint Contracts Tribunal (JCT) launched its new suite of building contracts in 2016 with updates to the entire JCT family completed in 2017.